Sequencing Activities and Dependencies

Getting dependency types right is the invisible groundwork beneath every schedule that later looks impossible to execute. This chapter covers the four types and why finish-to-start dominates most real schedules.

Before a schedule can be built, project activities must be sequenced according to their dependencies. The four common dependency types are finish-to-start, where one activity cannot begin until another finishes; start-to-start, where two activities must begin together; finish-to-finish, where two activities must end together; and start-to-finish, the least common, where one activity cannot finish until another begins [1].

Key Takeaways
  • The four dependency types are finish-to-start, start-to-start, finish-to-finish, and start-to-finish (the rarest).
  • Finish-to-start dominates real schedules because most work genuinely cannot start until a prerequisite is complete.
  • Correctly identifying start-to-start or finish-to-finish dependencies can reveal genuine opportunities for parallel work and compression.
  • Misrepresenting a real dependency as independent produces a schedule that is impossible to execute, regardless of effort applied.